Client: Volker Rail
Purpose: Support overhead structure to enable excavations
Ground Conditions: Made up ground, clay and gravel
Pile Type: 219mm
Depth: 9m
Quantity: 8
Additional Work: Grillage fabricated and installed
Location: Hackney, London
Completed: April 2017
The only option for this project was screwpiling.
Using this amazing machine with a 22m reach, we were able to install and support structures on both sides of the line to enable Volker to excavate in close proximity.
A great challenge with a great outcome.