Client: London Underground
Purpose: To underpin and support old location platform on embankment between LUL line and Network Rail
Ground Conditions: Unknown backfill clay
Pile Type: 60r
Depth: 5m
Quantity: 4
Additional Work: None. Supporting structure placed on top of the piles done by others
Location: Wimbledon
Completed: October 2015
This a great example for this clever hand install system.
As you can see there is not a lot of room to spare.
The material and equipment were sent out at night whilst trains were not running.
Under the use of lookouts and a coss this job was completed in under 5 hours and ready to take the load of the supporting structure.
- No disruption
- No mess
- No problem
- Happy client