Civil

Case study

Braced Elevated Concrete floor

Client: Private
Purpose: Raised braced concrete floor (wooden props for temporary floor support)
Ground Conditions: fill and chalk
Pile type: 89mm
Depth: 6m
Quantity: 12
Additional work: None
Location: HMP Winchester

HMP Wincher need to up date security, being tight for space there were few options to attach this unit to the existing building, Adding to problems its on a sloping site.

Using screw piling attached to a steel frame capped with the Hody profiled sheets (https://www.cdi-icm/system/hody) steel deck floor system enabled a raised braced concrete floor ready to land the new scanner unit.

Screw piles, steel frame and Hody floor installed in approx 5 days ready for concrete pour.

Fast, clean and strong

Gallery

Releveant Case Studies

Below are some similar case studies we have worked on.

Domestic
London Clay
89mm
Domestic
Sandy Clay into gravels
114mm