Coop Eco Store

Client: HPS
Purpose: New Store to be built in a new community with the aim of a low impact build on the Environment
Ground Conditions: Clay
Pile type: 140mm
Depth: 4-8m
Quantity: 56
Location: Bucks

Coop approached the main contractor for the supply and installation of low carbon foundations. If required these piles can be removed, re used or recycled.

We installed these foundations in 5 days start to finish

Gallery

Releveant Case Studies

Below are some similar case studies we have worked on.

Civil
fill and chalk
89mm
Domestic
London Clay
89mm