Civil

Case study

Elevated Structure with concrete slab

Client: Private
Purpose: Elevated concrete floor for new scanner unit
Ground Conditions: Clay
Pile type: 89mm
Depth: 6m
Quantity: 16
Additional work: None
Location: Huntingdon

Customer need to extend existing footprint of the premises, due to the area being approx 600mm lower using screw piles eliminated the need for considerable floor build up but more importantly time.

Screw piling, steel frame and Hody profiled sheets ( https://www.cdi-icm/system/hody/) installed in 5 days ready for mesh and concrete pour to a depth of 130mm

Gallery

Releveant Case Studies

Below are some similar case studies we have worked on.

Civil
fill and chalk
89mm
Domestic
London Clay
89mm
Domestic
Sandy Clay into gravels
114mm