Civil

Case study

Pod Track

Completed: March 2023
Client: Pod Track
Purpose: Stair case for access to switch equipment and track
Ground Conditions: Made fill
Pile type: 89mm
Depth: Variable due to changing ground conditions
Quantity: 20
Additional work: None
Location: Taplow

Due to the steep bank and rail line needing to stay running a long reach installation was required for new stair case installation to gain access to the track safely. We used this machine to its full capacity of 22m

Gallery

Releveant Case Studies

Below are some similar case studies we have worked on.

Civil
fill and chalk
89mm
Domestic
London Clay